The short answer
Every major development in London must submit a detailed energy assessment with its planning application, showing how it will meet the London Plan's net zero-carbon target. The assessment follows the energy hierarchy: be lean (use less energy), be clean (supply energy efficiently), be green (generate renewables on site) and be seen (monitor the result). Building Regulations set the minimum, and planning policy often asks for more. Outside London, the rule depends on the local plan: see councils outside London.
Sources: The London Plan 2021, GLA Energy Assessment Guidance (June 2022)How planning and Building Regulations differ
| Building Regulations | Planning (London Plan and local plan) | |
|---|---|---|
| Decided by | Building control body | Local planning authority, with the GLA for referable schemes |
| Question asked | Does the design meet the minimum legal standard? | Does the scheme meet policy targets and maximise on-site savings? |
| Timing | Before and during construction | At application, and by condition afterwards |
| Applies to | All building work in scope | Usually major development (thresholds vary) |
The London Plan policies that matter
- SI 2: Minimising greenhouse gas emissionsLegal requirementThe energy hierarchy and the net zero-carbon target. Major proposals need a detailed energy strategy.
- SI 3: Energy infrastructureLegal requirementThe heating hierarchy and Heat Network Priority Areas.
- SI 4: Managing heat riskLegal requirementOverheating and the cooling hierarchy.
- T6.1: Residential parkingLegal requirementEV charging provision in new homes, alongside Part S.
Planning policy, not Building Regulations. Full text in The London Plan 2021, chapter 9.
What the GLA energy assessment guidance asks for
These figures are from the GLA Energy Assessment Guidance (June 2022), written for Part L 2021. The GLA has said it will update its approach once new national standards are agreed, so check for a newer edition before you rely on them.
| Item | Requirement | Para |
|---|---|---|
| On-site carbon reduction | At least 35% beyond Part L 2021, met separately for residential and non-residential parts | 1.7, 2.2 |
| Residential benchmark | 50% or more beyond Part L 2021 expected | Table 1 |
| Energy efficiency (be lean) | At least 10% for residential and 15% for non-residential from efficiency alone | 1.7, 7.1 |
| Energy use intensity | Report it. Reference figure for residential is 35 kWh/m²/yr | Table 4 |
| Space heating demand | Report it. Reference figure is 15 kWh/m²/yr | Table 4 |
| Overheating | Show the cooling hierarchy was followed, with passive design | 8.2 to 8.4 |
| Heat networks | Show connection to existing or planned networks was prioritised, with correspondence | 9.12, 9.13 |
| Renewables | Commit to maximising on-site generation, including storage potential | 1.7 |
| Timing | Submitted with the application, not left to a condition | 1.7 |
| Outline applications | Energy strategy at outline, detailed assessment at reserved matters | 3.2, 3.6 |
Offsetting the remaining carbon
Any shortfall to zero carbon is bought out through a payment to the borough's carbon offset fund. Guidance has used 30 years of remaining emissions multiplied by a price per tonne, with £95 per tonne recommended. Boroughs may set their own price. A payment is accepted only once on-site savings are shown to be maximised.
Our practical advice Check your borough's current offset price before you budget.
Heating and solar in a planning application
- In Heat Network Priority Areas, connect to an existing or planned network first. Then zero-emission or secondary heat (with a heat pump if needed), then low-emission CHP only where it enables a wider network, and ultra-low NOx gas boilers last.
- Direct electric heating is generally not accepted.
- Solar PV should be maximised on roofs even if the 35% target has been met.
- "Be seen": all major developments must monitor and report energy performance after completion.
- Whole life-cycle carbon assessments are required for referable applications.
Some of these points come from older GLA guidance, so confirm each against the current edition.
Borough policies and the Merton rule
The Merton Rule, adopted by Merton Council in 2003, was the first policy requiring a share of energy from on-site renewables. It has largely been absorbed into London Plan and borough policy, but boroughs still add their own requirements. Examples include Merton's adopted 2024 Local Plan climate policies, and a group of London boroughs working on net zero policies that use energy-use targets instead of percentage carbon savings. Read the adopted local plan for each site.
Outside London
Councils outside London set their own energy policies in their local plans, within national limits. We cover the legal powers, the national limits and real council examples on a separate page: Energy strategies: councils outside London.
How the Future Homes Standard changes things
From 2027, the Building Regulations will already require low-carbon heating and solar on new homes. Planning applicants will still be asked to follow the energy hierarchy and show maximised on-site savings, and GLA guidance is expected to move toward the new baseline.
Our practical advice Do not assume that compliance with Part L alone satisfies planning policy.
What a good energy statement contains
- Site and scheme summary, including units, floor area and uses.
- Baseline emissions and the method (SAP or SBEM, and the emission factors used).
- Be lean measures and the percentage achieved.
- Be clean: heat network opportunity and the heating hierarchy.
- Be green: heat pump and PV design, with roof layouts.
- Overheating and the cooling hierarchy.
- Energy use intensity and space heating demand figures.
- Offset calculation and any payment.
- Be seen monitoring commitment.
- Whole life-cycle carbon, where required.
Recommended installer Partner
Get it installed by REX
Your energy strategy will commit to heat pumps and solar. REX installs the systems your strategy promises, so what is built matches what was approved.