The short answer
From 24 March 2027, new homes in England must be designed to a new Part L that requires low-carbon heating and on-site renewable electricity. A plot keeps the old rules only if its building control application is in before that date and work starts before 24 March 2028.
Sources: Building Circular 01/2026, Approved Document L Volume 1 (2026)Key dates
| Date | What happens | Source |
|---|---|---|
| 24 March 2026 | Regulations and revised Approved Documents published | Circular 01/2026 |
| 24 March 2027 | Regulations come into force Next | Circular 01/2026 |
| 24 September 2027 | Start date for higher-risk building work | Circular 01/2026 |
| 24 March 2028 | Last day to start work on a plot protected by an earlier application | Circular 01/2026 |
Many blogs say the rules apply "from 2028". The government circular gives 2027 as commencement, with 2028 as the end of the transition.
What the standard requires
- Low-carbon heatingLegal requirementThe notional dwelling used to set targets includes a heat pump, so gas boilers are not banned by name but will struggle to meet the targets. Heat networks with low-carbon heat are a second route.
- On-site renewable electricity (Requirement L3)Legal requirementMost homes need PV equal to an array covering 40% of the ground floor area at 0.22 kWp/m².
- Fabric and servicesLegal requirementTargets cover primary energy, emissions and fabric efficiency. Fabric still matters because it sets how big the heat pump and PV need to be.
- Ventilation and overheatingOfficial guidanceApproved Document F (ventilation) was revised alongside Part L. Part O (overheating) continues to apply.
- Evidence at completionLegal requirementThe as-built energy report (BREL), a measured air permeability result, commissioning records and a Home User Guide for the owner (new regulation 40C).
Transitional rules in plain English
- Rules are applied plot by plot, not site by site.
- A plot keeps the old rules if the initial notice, building notice or full plans application is given before 24 March 2027.
- Work on that plot must also start before 24 March 2028.
- Miss either condition and the new Part L applies to that plot.
Our practical advice Plots you cannot start by March 2028 should be designed to the new standard now.