The short answer
EV chargers, heat pumps and solar can each meet the Building Regulations and still stall on the electricity connection. New developments usually need a connection offer from the local network operator (the DNO) sized for the combined load. The developer pays for the new assets and may pay for reinforcement. Small domestic solar is notified to the DNO after commissioning, while larger or multiple installations need approval first. Electrical work in dwellings must meet Part P and BS 7671.
Sources: National Grid: connections for homes and small businesses, ENA joint EV charge point and heat pump formWhich route applies
| Equipment | Typical DNO route | Notes |
|---|---|---|
| New supply to a development | Apply for a new connection | Developer pays for contestable assets and may pay reinforcement costs |
| Solar or battery up to G98 limits (16 A per phase, type-tested) | Notify the DNO within 28 days of commissioning | The installer usually does this |
| Solar, battery or generation above G98, or multiple premises | Apply before installing, under G99 | See the multiple-premises G98 guide |
| EV charge points and heat pumps added to existing supplies | Connect and notify, or apply, using the joint ENA form | Depends on supply size, heat pump demand and charge point output |
| Several EV chargers and heat pumps at once | Multi-install form | Used by installers for developments |
Sources: National Grid: connections for homes and small businesses, National Grid: industrial, commercial and generation hub, SSEN: G98 multiple-premises summary guide, ENA joint EV charge point and heat pump form. Thresholds and forms differ by DNO. Use the ENA "Who is my network operator" lookup for your postcode. London is mainly served by UK Power Networks.
The connect-and-notify test for chargers and heat pumps
The ENA joint form sets the criteria for when an installer can connect first and notify after. The checks include:
- Whether the supply is above 60 A (13.8 kVA) per phase.
- Whether the total heat pump maximum demand is 32 A or less.
- Whether the heat pump model is on the ENA heat pump database.
- Whether the combined EV charge point output is 30% or less of the maximum import capacity.
If a check fails, the installer applies to the DNO first. Always use the current form and criteria from your DNO.
Planning the load
Government research on new-build networks uses these working assumptions:
- A typical EV charge point draws about 7.4 kW at full load.
- A 5 kW (heat) heat pump for a one or two bedroom home draws about 2.4 kW of electricity at full load. Electrical load is lower than heat output.
Source: Scottish Government: electricity network constraints research. It is Scottish research, but the engineering assumptions are general.
Our practical advice Use diversity assumptions agreed with the DNO, and plan load management so chargers, heat pumps and other loads stay within the supply.
Who pays
A developer generally pays the full cost of contestable work, meaning new assets installed for the sole use of the development, and may pay for reinforcement of the wider network needed to supply it. Connection charging in England and Wales is set by Ofgem and each DNO's connection charging statement, so check those before budgeting. Summary: Scottish Government research: who pays for connections.
Solar and export limits
Requirement L2 of Part L says on-site generation must be sized appropriately for the site and infrastructure, which can include export limits set by the DNO. Where a limit stops the reference array from being installed, record it as evidence for building control. See solar PV and batteries.
Electrical safety: Part P and BS 7671
- Part PLegal requirementCovers electrical safety in dwellings in England. Approved Document P points to BS 7671 as the way of showing compliance, and Approved Document L says Part P applies to on-site generation and storage.
- Notifiable workLegal requirementShould be done by an installer registered with a competent person scheme (such as NICEIC or NAPIT), who can self-certify. Otherwise building control must be notified.
- BS 7671 Amendment 4Official guidanceBS 7671:2018+A4:2026 updated the rules for electrical energy storage, EV charging and other modern installations, including where batteries can go. See the Electrical Safety First: BS 7671 Amendment 4 pocket guide, and check the standard itself before siting batteries.
- Competent person schemes and MCSOfficial guidanceA competent person scheme lets a business self-certify Building Regulations compliance. MCS certifies products and installers for consumer protection and incentives, covering solar and batteries up to 50 kW and heat technologies up to 45 kW. See the Competent person schemes: current list.
Recommended installer Partner
Get it installed by REX
Fitting EV chargers, heat pumps and solar on the same supply? REX installs all of them, so one installer looks at the combined load.
Developer checklist
Common questions
Do I need DNO permission to install solar on a new home?
Small G98 systems are notified within 28 days of commissioning. Larger or multiple installations need approval first, under G99.
Who pays for network reinforcement?
The developer pays for contestable assets and may pay for reinforcement of the wider network, under the DNO's connection charging statement.
What is the difference between G98 and G99?
G98 covers small type-tested generation up to 16 A per phase, notified after commissioning. G99 covers anything larger, or multiple premises, and needs approval before installation.
Sources
- National Grid: connections for homes and small businesses
- National Grid: industrial, commercial and generation hub
- SSEN: G98 multiple-premises summary guide
- ENA joint EV charge point and heat pump form
- Scottish Government: electricity network constraints research
- Scottish Government research: who pays for connections
- Competent person schemes: current list
- Electrical Safety First: BS 7671 Amendment 4 pocket guide