The short answer
From 24 March 2027, a new dwelling must have an on-site renewable electricity system under new Requirement L3. The default size is a reference array of 0.22 kWp per m² covering 40% of the ground floor area. If the roof cannot take that, the design must maximise output, and the evidence goes to building control. Batteries are not required.
Sources: Approved Document L Volume 1 (2026), Approved Document L FAQHow the L3 size is worked out
The rules are in Approved Document L Volume 1 (2026), Section 5, with worked layouts in Appendix B.
| Item | Rule | Reference |
|---|---|---|
| Reference array | 0.22 kWp per m² over an area equal to 40% of the ground floor area | Para 5.73a |
| Sizing formula | PV output = PV area (at least 40% of ground floor) × efficiency (at least 0.22 kWp/m²) | Equation 5.1 |
| Reference orientation | South-east to south-west, 45° pitch, unshaded | Para 5.73a |
| Alternative test | Annual output equal to an array covering the "reasonably practicable roof area" at 0.22 kWp/m² | Para 5.73b |
| If the standard cannot be met | Maximise output, for example with higher-efficiency panels or different orientations | Para 5.76 |
| Minimum shortfall threshold | A shortfall is allowed where the roof cannot produce 720 kWh a year (houses) | Para 5.77 |
| Reporting | Non-compliant arrays are flagged in the as-built (BREL) report with evidence | Para 5.78 |
Output is calculated, not just area. The method uses the SAP 10.3 approach in Appendix M1, so orientation and shading affect the result. Panel efficiency is peak output divided by the whole panel area, including the frame.
When L3 does not apply
The requirement does not apply where the building is a relevant building under regulation 7(4), where a system is not possible because of the design or surroundings, or where equivalent output comes from an off-site system serving the residents.
Our practical advice Treat these as exceptions you have to evidence, not ones you can assume.
What building control will want to see
Where output is below the reference standard, Appendix B asks for:
- Roof diagrams with and without PV.
- A statement explaining the lower provision.
- Calculations signed by a suitably qualified person, such as an On Construction Domestic Energy Assessor.
- The maximum capacity (kWp) and annual generation (kWh) possible for the roof layout and orientation.
Roof layout rules of thumb
Appendix B uses these offsets to size the usable roof area. They are guidance, not meant to cover every case.
| Offset | Distance |
|---|---|
| From the ridge or top of the pitch | 600 mm |
| From the roof edge | 500 mm |
| From the centre line of a party wall | 750 mm |
| From windows or doors | 500 mm |
| Maintenance access from an unprotected edge | 2,000 mm, or 300 mm with a man-safe system or railings |
Worked examples in the document: a hipped roof with a 16 m² array gives 3.52 kWp, and a mid-terrace with dormers and an 8 m² array gives 1.76 kWp.
Questions developers ask
- Detached garagesOfficial guidanceThe garage roof does not count towards the dwelling's roof area, and the garage floor is excluded from the 40% calculation. Panels on a garage in the curtilage can still be used to meet L3.
- North-facing or shaded roofsOfficial guidanceUnlikely to be excluded on that basis alone, because the calculation already accounts for orientation and shading.
- Blocks of flatsLegal requirementParagraph 5.74 sets the output for buildings with several dwellings. Read it before designing a block.
- Grid limitsLegal requirementRequirement L2 still applies: the system must be sized for the site and infrastructure, which can include DNO export limits. See grid connections.
- BatteriesOfficial guidanceNot required by L3. If fitted, they fall under Approved Document P, and MCS covers electrical storage up to 50 kW.
Planning permission
For houses and flats, permitted development rights changed on 27 August 2026. Until 27 August 2027 you can use either the old or the new rules.
| Condition | Houses (from 27 Aug 2026) | Blocks of flats |
|---|---|---|
| Roof panels (pitched) | No more than 200 mm from the roof slope | Same |
| Wall, balcony or enclosure facing a highway | No more than 0.2 m | No separate rule |
| Elsewhere on a wall or balcony | No more than 0.4 m | No separate rule |
| Flat roof | No more than 600 mm above the highest part | Same |
| Listed buildings and scheduled monuments | Not permitted | Same |
| Conservation areas | No panels on a wall, balcony or enclosure facing a highway | No panels on a wall facing a highway |
| Plug-in solar | New rights; not on timber walls, balconies or timber-clad exteriors | Same |
Source: Planning Portal: solar equipment on houses and flats. New homes also need the solar shown in the planning approval, and London schemes follow the London Plan energy rules (see renewable energy strategies).
Export payments, certification and VAT
Smart Export Guarantee payments go to the homeowner once the system is registered. Licensed suppliers must offer an export tariff, and an installation certificate such as MCS is normally needed. The zero rate of VAT for installing solar in existing homes ends on 31 March 2027, after which the reduced 5% rate applies. Energy-saving materials installed while building a new dwelling are already zero-rated.
Recommended installer Partner
Get it installed by REX
Need an L3 array designed and fitted? REX installs solar PV and batteries on new homes and blocks of flats.
Developer checklist
Common questions
Does every new home need solar panels?
From 24 March 2027, most do under Requirement L3, unless an exception applies and is evidenced. Plots protected by the transitional rules follow the old Part L.
Do new homes need a battery?
No. Batteries are optional. If fitted, they must meet the electrical rules.
Can a north-facing roof get out of the requirement?
Not on its own. Orientation is already part of the calculation, so the design must maximise what the roof can produce.